Building progress as at 23rd August 2020

 

 

We are proud to announce construction of Nautico Manly is complete. Brand new residences are now open for inspection. To find out more, please contact Jo Prince-Gillies on 0448 911 016 or Simon Chipman on 0473 938 180 at McGrath Projects. 

 

 

 

Building progress as at 23rd July 2020

 

– Privacy screens to select residences have been manufactured and installed 

– Planter boxes to select residences are underway

  Floorboards have been installed to all ground floor and level 1 residences

– Floorboard installation has commenced to penthouse level residences

– Skirting boards and architraves have been installed to ground floor and level 1 residences

 

 

– Tiling to all bathrooms and laundries is complete

– Instantaneous hot water systems have been installed to all residences 

– Plumbing fixtures to bathrooms have been installed e.g toilets, shower rails + heads, shower mixers, basin mixers, stone wall basins and stone free-standing baths

– Wall hung mirror cabinets installed to all bathrooms

– Installation of shower screens to ground floor and level 1 residences has commenced

– Installation of kitchen cabinetry to all residences is complete

– Stone bench tops and tiled splash backs have been installed to all kitchens

– Appliances have been installed to all ground floor residences, level 1 and 2 are underway

– Electrical works are almost complete (down lights, LED strip lights to kitchens and bathrooms, pendant lights, ceiling fans, power points and light switches)

– Air conditioning installation is almost complete

– Interior painting to all residences is almost complete

– Tiling to all balconies is almost complete

– Balustrades have been installed

– All internal doors have been installed complete with door hardware

– Wardrobe cabinetry and sliding doors have been installed

– External rendering and painting to the building is almost complete

– Fire rated entry doors and door locks to all residences have been installed 

– Pole transformer has been delivered and connected (Energex)

– Mains power connected to the building

– Lift construction and installation complete

– Storage cages have been installed in the basement

– Basement mechanical ventilation almost complete

– Basement roller door installed

– NBN connection to the building is underway

 

 

 

Building progress as at 23rd May 2020

 

Rendering of external walls is almost complete and painting of the building is making progress. The scaffolding has started to come down revealing Nautico Manly's architecturally designed features. 

 

 

Progress is being made with the installation of kitchen joinery and wardrobes to bedrooms for all ground floor and level 1 residences. 

 

 

Our beautiful free standing matte white stone bathtubs and stone wall basins are being installed in Nautico's fully tiled luxury bathrooms. 

 

 

Large glazed windows and doors have been installed to all penthouses. 

 

 

Building progress as at 23rd April 2020

 

We are nearly at lockup stage as the roof structure is nearing completion with rafters, purlins and roof sheets installed

Ground floor and level 1 windows and glazed doors have been manufactured and installed. Windows and glazed doors on the penthouse level are currently being installed on site

 

 

Check measure has been completed for ground floor and level one cabinetry. Cabinetry is currently being manufactured locally and soon to be installed on site 

Internal doors, skirting boards and architraves have been installed to ground floor units


Waterproofing of all wet areas has been completed and tiling has commenced

 

 

Plasterboard for ground floor is complete

Level 1 plasterboard has commenced

 

 

Building progress as at 23rd March 2020

 

Framing has commenced on level 2 penthouse residences


Door and window openings to level 2 penthouses have been waterproofed ready for window installation

 

 

Ceilings and partitions are underway with framing to the ground floor and level 1 complete


Electrical and plumbing rough-ins for ground floor and level 1 are complete

 

Level 2 building progress as at 23rd February 2020

 

Level 2 party walls set out and laid

Concrete poured and core filled for all level 2 party walls

 

 

Level 2 steel installed and tied


Level 2 slab poured


Level 2 electrical and plumbing conduits installed

 

 

 

Level 1 building progress as at 23rd January 2020

 

Level 1 steel installed and tied


Level 1 electrical and plumbing conduits installed


Level 1 slab poured

 

 


Level 1 party walls set out and laid


Edge boards stripped


Columns built and poured


Strip formwork from level 1 slab and backprop


Block walls on level 1 core filled with concrete

 

 

Setting the formwork for level 2 slab 

 

Ground floor building progress as at 23rd December 2019

Time lapse footage of concrete being poured for the ground floor slab.

 

 

Concrete pump arriving on site to pour the driveway.

 


Ground floor C and D steel layers tied and installed

Ground floor concrete slab poured


Ground level party walls set out and laid


Edge boards stripped

 

 

All hands on deck today! Below we can see formwork being set up for the ground floor slab.

 

 

Formwork

 

 

Basement works as at 23rd November 2019

 

– Permanent electricity was connected to the basement


Air vents to basement completed and installation of mechanical ventilation installed


Stormwater Detention tank has been formed, poured and waterproofed

Door frames installed in the basement

 

 

Concrete columns and all basement walls completed

A and B podium slab steel layers tied and installed

Podium slab formed and poured

 

 

Excavation, foundations and services progress
as at 23rd September 2019

 

In-ground storm water has been completed

Sewer lines have been completed

All strip and pad footings completed

 

 

Piers, columns and all retaining walls are complete

The lift shaft has been dug, steeled and poured

 

 

Water mains work completed

Excavation completed and all spoil removed from site